Prime contractors, have you ever submitted a subcontractor’s claim to a public owner? Subcontractors, have you ever wanted to submit a claim against the government, but you had no contract with the government?
Generally, if the prime has or could have at least some liability (even potentially), then the prime can “pass-thru” the sub’s claim against the government.
A pass-thru claim will fail if the prime has severed or extinguished all liability for the claim between itself and its sub. This can be done by language that may already be in the subcontract or by a later agreement of release or settlement.
But, the same subcontract with the right language or a later agreement between the prime and sub (e.g., liquidation agreement) can preserve liability to keep a pass-thru claim alive.
A short success story:
A prime contractor on a project in Slick Rock, Colorado for the U.S. Dept. of Energy agreed to remediate uranium mill tailings. The prime submitted a pass-thru claim by one of its subcontractors against the Government (the Sub’s claim “passed-thru” the Prime to the Government).
The Government’s efforts to dismiss the claim failed because the prime had to pay whatever recovery it got from the Government to the sub. Only when the recovered amount (no matter how small) was paid, by the Government to the prime and then from the prime to the sub, was the prime’s liability extinguished. Until that point, the fire of the claim kept burning.
M.K. Ferguson Co., et al. v. U.S., Ct. Fed. Claims, No. 12-57C (April 14, 2016)
Roads & Bridges | All According to Plan
ALL ACCORDING TO PLAN | Exact Measurements Go a Long Way
In December 2013, a contractor agreed to replace four bridges for the […]
Roads & Bridges | Connecting the Dots
CONNECTING THE DOTS | Showing Causation in Contracting Cases is Critical
In this asphalt case, the prime contractor agreed to perform a $13 […]
Roads & Bridges | Liquidated Damages
LIQUIDATED DAMAGES | Penalties and What is Unenforceable
Liquidated damages typically flow from delays, but they are not always solidly enforced.
In June 2017, […]
Roads& Bridges | Warranty Provisions
WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results
You are responsible for things within your control. Be careful if […]
Roads& Bridges | The Agreed Price
THE AGREED PRICE | This case stands as a warning about pay-if-paid clause
History cannot be rewritten and a bad, but legal, […]
Roads& Bridges | Confusing Waters
CONFUSING WATERS | A Supreme Court ruling leaves room for ambiguity
What happens when there may be a “significant nexus” between “adjacent” and/or […]
Roads & Bridges | Authority Defined
AUTHORITY DEFINED | The Law of Agency is Important to Understand
For any project, this Russian proverb is helpful: Doveryay, no proveryay – […]
Jurisdiction is Power
Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). […]
Roads & Bridges | Defining Labor
DEFINING LABOR | How the Miller Act continues to shape the industry
In the late 1700s, risks of nonpayment caused a shortage of […]