Suppose that you (the Contractor) had extra costs and want payment for those extra costs from the designer. But,
- No property was damaged,
- Nobody got hurt (thankfully), and
- There is no contract between you and the designer.
Likely Result: You cannot recover from the designer because of the economic loss doctrine, which usually applies when the facts listed above are true.
Possible Solutions:
- Carefully negotiate your scope of risk under the contract;
- Trust but verify (consider using an independent design reviewer pre- or post-bid and pre-construction);
- Manage, coordinate, and communicate; and/or
- Apply an exception to the rule (depending on which State you’re in and the unique facts of the scenario).
Here’s a recent example from the highest court of Maryland where the contractor (unfortunately) lost:
Under a contract with the City of Baltimore, the Contractor agreed to construct improvements to a wastewater treatment plant including construction of giant concrete tubs to hold untreated wastewater. The Contractor constructed the tubs per the third-party engineer’s design, but the tubs leaked. The Contractor sued the engineer for money damages, no persons were injured and no property was damaged from the leaking tubs.
The highest court in the State of Maryland denied the Contractor’s recovery from the engineer. The court denied the contractor’s request for two main reasons. First, the City, Contractor, and engineer had carefully limited their risk by the complex construction contracts, so there was no need for the court after-the-fact to adjust the limits of that risk. Second, adjusting the limits of the agreed-upon risk could result in higher costs for future public construction projects and, since public projects are often funded with taxpayers’ dollars, then taxpayers would be funding the potentially higher costs. [Editorial note: I generally agree with the court’s first reason, but find the second reason flimsy.]
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, 451 Md. 600 (2017)
Roads & Bridges | All According to Plan
ALL ACCORDING TO PLAN | Exact Measurements Go a Long Way
In December 2013, a contractor agreed to replace four bridges for the […]
Roads & Bridges | Connecting the Dots
CONNECTING THE DOTS | Showing Causation in Contracting Cases is Critical
In this asphalt case, the prime contractor agreed to perform a $13 […]
Roads & Bridges | Liquidated Damages
LIQUIDATED DAMAGES | Penalties and What is Unenforceable
Liquidated damages typically flow from delays, but they are not always solidly enforced.
In June 2017, […]
Roads& Bridges | Warranty Provisions
WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results
You are responsible for things within your control. Be careful if […]
Roads& Bridges | The Agreed Price
THE AGREED PRICE | This case stands as a warning about pay-if-paid clause
History cannot be rewritten and a bad, but legal, […]
Roads& Bridges | Confusing Waters
CONFUSING WATERS | A Supreme Court ruling leaves room for ambiguity
What happens when there may be a “significant nexus” between “adjacent” and/or […]
Roads & Bridges | Authority Defined
AUTHORITY DEFINED | The Law of Agency is Important to Understand
For any project, this Russian proverb is helpful: Doveryay, no proveryay – […]
Jurisdiction is Power
Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). […]
Roads & Bridges | Defining Labor
DEFINING LABOR | How the Miller Act continues to shape the industry
In the late 1700s, risks of nonpayment caused a shortage of […]